Finishers at Work

After more than 2 months of waiting, the additional bamboo plywood needed to continue built-in construction at the River House finally arrived. I cut all the panels needed to complete the drawer fronts and cabinet doors for the laundry, mudroom, and shop and the front panel for the flush-mounted freezer in the pantry. Jeanine and Susan worked together to apply finish to some two dozen panels leaving them ready for installation. I also started replacing the temporary stairs from the back hall to the garage with the final design that includes provisions for a future wheelchair ramp should that ever be needed. An additional shipment of plywood for the indoor stair railing is scheduled to arrive tomorrow, weather permitting. With any luck, we will be ready for our occupancy inspection during the first week of the new year.